Carlos Torres

Building a 500 sq ft addition onto an existing structure from excavation, foundation, framing, and ultimate completion of the project.

  • Contract ID: #7255
  • Start Date: 06/05/24
  • End Date: 09/15/24
  • Value: $92,000
  • Contact Phone: Provided upon request

3x Homes: Seth Scott

Interior demolition of wood floor, concrete basement floor cutting and demolition, excavation, native surface compaction, concrete preparation.

  • Contract ID: 7267A
  • Start Date: 05/15/24
  • End Date: 05/29/24
  • Value: $34,450
  • Contact Phone: Provided upon request

Greg and Hellen Butler

Bathroom remodel: demolition, rough electrical, rough plumbing, framing, tile work, electrical/plumbing/finish work.

  • Contract ID: 7248
  • Start Date: 02/08/24
  • End Date: 03/15/24
  • Value: $33,703.62
  • Contact Phone: Provided upon request

Weber State University

Replaceing several yards of concrete around the University while maintaining safety, barricades, and traffic. The job consisted of concrete, demolition, excavation, concrete prep, and concrete, finishing both in interior buildings and outdoor area areas.

  • Contract ID: 7396
  • Start Date: 06/26/25
  • End Date: 08/01/25
  • Value: $111,155.00
  • Contact Phone: Provided upon request